This is a current guideline for the build schedule at Thalassa so you are aware of approximate payment dates however, our accounts department will contact you individually when payment becomes due.
It is estimated that work will commence on blocks 8 – 1 from March 09
All skeleton works will be completed on blocks 9 - 21 by end of Feb 09 approximately
Blocks 9 & 10
Ground floor skeletons completed
1st floor apartments – approximately the end of Jan 09
Other floors – approximately end of Feb 09
Block 11
Ground floor – approximately end of Jan 09
Other floors – approximately end of Feb 09
Blocks 12 / 14 / 15 & 16
We expect all skeletons for these blocks to be completed by the end of Jan 09.
Blocks 10, 12 & 13 - 1st floor completed
We do occasionally have problems getting e-mails through to clients as we can be blocked so please do contact us, should you think that you haven't received any e-mails from us or a stage payment is due etc. Many thanks.