Thalassa Beach Resort
Estimated Completion Dates for Completion of Tiling & Windows


Block No. Stage Date
21 Windows Mid Nov 2009
21 Tiling Mid Nov 2009
20 Windows Mid Dec 2009
20 Tiling Mid Dec 2009
19 Windows Mid Dec 2009
19 Tiling Mid Dec 2009
18 Windows Mid Jan 2010
18 Tiling End Dec 2009
17 Windows End Dec 2009
17 Tiling Mid Dec 2009
16 Windows Mid Feb 2010
16 Tiling End Jan 2010
15 Windows Mid Feb 2010
15 Tiling End Jan 2010
14 Windows Mid March 2010
14 Tiling End Feb 2010
13 Windows Mid March 2010
13 Tiling End Feb 2010