Thursday, 5 February 2009

Update estimated build schedule - skeleton works only

We now anticipate that the following skeletons will be completed as follows:

Blocks 15, 14, 12, 10 and 9 to be completed by the end of Feb 2009

Block 11 ground & 1st floor level to be completed by the end of Feb 2009
Block 11 2nd & 3rd floor levels to be completed by the end of March 2009

Block 8 ground floor to be completed by the end of Feb 2009
Block 8 2nd & 3rd floor levels to be completed by the end of March 2009

Block 7 ground floor to be completed by the end of March 2009