Tuesday, 10 March 2009

Updated skeleton works schedule

Block 7 – G01, G02 & G03 completed

Block 8 – G01 – G04 completed

Block 5 & 6 Ground floor – end of March

Block 8 – apartments 101 – 304 – end of March

Block 11 – apartments 104 – 306 – end of March

Block 3 & 4 ground floor – end of April

Block 5 – apartments 101 – 203 – end of April

Block 6 – apartments 101 – 208 – end of April

Block 7 – apartments G05 – 304b – end of April

Skeletons complete – Block 9, 10, 12, 13, 14, 15, 16, 17, 18, 19, 20 & 21.