Block 7 – G01, G02 & G03 completed
Block 8 – G01 – G04 completed
Block 5 & 6 Ground floor – end of March
Block 8 – apartments 101 – 304 – end of March
Block 11 – apartments 104 – 306 – end of March
Block 3 & 4 ground floor – end of April
Block 5 – apartments 101 – 203 – end of April
Block 6 – apartments 101 – 208 – end of April
Block 7 – apartments G05 – 304b – end of April
Skeletons complete – Block 9, 10, 12, 13, 14, 15, 16, 17, 18, 19, 20 & 21.